Front Side Renovation Update
Update as of 11/02/08

Construction on the front side renovation began September 3, 2008. Facades of units were removed and photos below show what was discovered in the process.

Photos of Ongoing Front Side Construction

Click on photos to enlarge
Update of progress as of 11-02-08

Construction is now at
unit 710--4 more to go! >

 
Carport section prep and
new kitchen vents >
Ongoing Progress and
new numbers on deck fronts>
     
Update of progress as of 10-21-08
Front View Progress>
V

Damage Found and Restoration Unit 722

Damage Found >

Restoration >

Damage Found and Restoration Unit 720 >

Damage Found>
Restoration >

Damage Found and Restoration Unit 716

Damage Found and Restoration >

Damage Found and Restoration Unit 714

Damage Found>
 
Restoration>
Update of progress as of 10-05-08

Front view with siding and railing installed>

Damage found and restoration

Internal View of 722
rot found >

 
 

< repair

 

repair
v

Unit 726 damage found >
Unit 732 damage found>
723 damage found and fix >
Update of progress as of 9-22-08
Front view as of 9-22-08 >
 
Siding being installed on Unit 736 on 09-22-08>
Update of progress as of 9-13-08

Contruction begins >

Internal View of
Rot found >
  < second floor water damage at floor level
Infrastructure Replacement >

< Rot found

Infrastructure Replacement >

 

Check back for updates.